Menu

CASTELLÓN, ESPAÑA

EMERGENCY WORKS AND REPAIR OF MARIA CRISTINA DAM RELIEF

Working field

Renewable Energy

Client

BECSA, S.A.U.

Ending Year

2016

Budget

487.800,01 €

Technical assistance to the voluntary management of the project, with the following characteristics:

  • lifting of the flap of the bowl, on the part affected by the damage and up to the downstream end
  • sanitation of the area to reach the rocky limestone substrate
  • infill with escollera taken with concrete up to the level of support of the slab
  • installation of passive anchors
  • concreting of a 1 m thick reinforced concrete slab
  • dismantle and clear downstream of the basin of the spillway
  • repair of the wall of the right bank with reinforced concrete
  • embankment of the area immediately downstream of the spillway
  • running wall deflector at right cashier

FEATURED

PROJECTS