MEDITERRANEAN COAST, SPAIN

CONSTRUCTION DESIGN OF A BIOMETHANATION PLANT

Working field

Industrial Facilities, Renewable Energy, Waste Treatment

Client

Cliente privado

Ending Year

2026

Budget

28.000.000 € (PEM)

VIELCA INGENIEROS has prepared the construction design of a biomethanation plant for the treatment of approximately 97,000 tonnes per year of biowaste and sludge, split into two independent lines: around 64,000 t/year of organic waste and 33,000 t/year of sludge. The planned facility recovers these materials through anaerobic digestion and biogas upgrading to obtain biomethane for injection into the natural gas grid.

The organic line includes packaging separation, solid waste preparation and reception of pumpable materials. Digestion takes place in four heated digesters: two of approximately 6,000 m³ each for the organic fraction and two of around 1,800 m³ each for the sludge, with a combined volume of close to 15,600 m³. The associated gas holders have a combined capacity of approximately 6,500 m³.

The membrane upgrading system is sized for a biogas input of around 700 Nm³/h and a nominal biomethane production capacity of close to 405 Nm³/h, with a methane content of around 97%. The process includes gas pre-treatment, compression and quality control, as well as heat recovery to meet the needs of digestion and pasteurisation. The facility also includes photovoltaic generation for self-consumption.

The work carried out covers the definition of the general site layout and the design and definition of all civil works: earthworks, external works and access roads, buildings and structures, architectural design, utility networks, electrical installations, instrumentation and control, and fire protection. Technical assistance was also provided for the process engineering.