The project involves supervising the design, construction, equipping, and commissioning of the new Southern Regional Hospital in Choluteca, Honduras, located in the municipality and department of Choluteca on a site covering 55,750 m² equivalent to 8 mz.
The project is being developed using the fast-track methodology under a turnkey contract.
The healthcare facility will consist of two levels with a construction area of 14,357 m² and a capacity of 159 beds, of which 140 are census beds and 19 are non-census beds.
The hospital will feature the following service areas:
- Emergency (adult and pediatric)
- Internal medicine
- Surgery
- Intensive Care Unit
- Surgical Suite (4 Operating Rooms)
- Imaging: CT scanner, mammography unit, ultrasound, X-ray, fluoroscopy, and conventional radiography.
- Day hospital
- Outpatient Clinic
- Laboratory and Blood Bank
- Medical Residency
- Family Shelter
Type of services provided
Control and Monitoring:
- Supervision of the project’s design phase.
- Supervision of the project execution phase.
- Supervision of the Project’s Equipment Phase.
- Supervision of the commissioning phase.
Drafting of documentation:
- Preparation of weekly, monthly, and quarterly progress reports on the activities carried out.