Menu

LA POBLA DE VALLBONA, VALÈNCIA

URBANIZATION PROJECT OF SECTOR R-25 IN POBLA DE VALLBONA

Working field

Transport infrastructure

Client

AIU SECTOR R-25 DE LA POBLA DE VALLBONA

Ending Year

2022

Budget

7.393.661,47 €

Drafting of the Construction and Urbanization Project of the works in the sector R-25 and the redevelopment of the adjacent streets in the urban area of the municipality of Pobla de Vallbona.

The work carried out was as follows:

  • Definition of the layout and dimensioning of firm surfaces and pavements of roads, sidewalks and bike lanes.
  • Sanitation, water supply and rainwater networks.
  • Lighting networks, low-voltage, medium-voltage power lines and transformation and telecommunications centres.
  • Gas network.
  • Design of green areas and irrigation networks.
  • Urban equipment and furniture.
  • Calculation of the drinking water tank structure of 600 m3.

FEATURED